Simple Traccar calendar for scheduled reports

Cristian2 months ago

Can I use a simple Traccar calendar, for scheduled reports, but define at what time it runs, to avoid all scheduled reports running at the same time. I have several scheduled reports and they run at the same time crashing the server.

Anton Tananaev2 months ago

Scheduled reports run at the end of the calendar event.

Cristian2 months ago

Anton, in the attached example it would run at the time indicated by the red arrow?
https://ibb.co/k5RHxbq

Anton Tananaev2 months ago

The screenshot is not in English, so I don't know if it's a valid calendar for this use case.

Cristian2 months ago

It is now in English
https://ibb.co/VSKncCk

Anton Tananaev2 months ago

This doesn't look like a valid calendar for scheduling reports. Your from and to span multiple days, but then you're asking to generate reports weekly on Mondays and Tuesdays. I don't know how you expect this to work, but it most likely won't.

Cristian2 months ago

I am trying to understand how it works but I think I have it.
in this case I will receive a report on Sunday 31 between 22:00 and 22:15 hrs, weekly from Monday to Sunday.

https://ibb.co/m01xJ6j

Anton Tananaev2 months ago

No, it doesn't look right.

Cristian2 months ago

I was able to do what I needed
I created a calendar on this page https://ical.marudot.com/# , exported it in ics format and then uploaded it to traccar as a custom calendar.
I received the email with the week's trips from the device I created a scheduled report assigning the custom calendar to.
https://ibb.co/9gjF9db

Cristian2 months ago

If I schedule the recurrence of the report the email does not arrive, but just by removing the recurrence the email arrives with the date range that corresponds and at the time it is scheduled to be sent.
I have switched to Thunderbird thinking that it could be a problem of the program I am using to create the calendar, but the same thing happens.
https://ibb.co/0nfj5gM